| Name | Duration |
|---|---|
| prepare stage 1 landscape plan | 85.0 |
| Owner approves landscape plan | 5.0 |
| prepare landscpape documents | 10.0 |
| obtain landscape tender | 10.0 |
| stage 1 construction | 158.0 |
| owner approves | 5.0 |
| implement landscaping | 20.0 |
| Villa 1A COMPLETED | 1.0 |
| construction completed | 1.0 |
| install FF&E | 1.0 |
| code of compliance approved | 1.0 |
| design Villa 3B | 15.0 |
| Owner approves design for Villa 3B | 10.0 |
| Owner instructs Stage 2 proceed | 1.0 |
| review contract documents for Villa 1A | 5.0 |
| architectural drawings Villa 3B | 25.0 |
| collate documents | 5.0 |
| Structural drawings for Villa 3B | 20.0 |
| Prepare electrical reticulation proposal | 20.0 |
| Owner accepts PP proposal | 5.0 |
| submit application to Aurora | 5.0 |
| authorisation | 20.0 |
| prepare civil drawings | 15.0 |
| estimate for Civil work | 10.0 |
| Owner approves civil drawings | 5.0 |
| call tenders for services | 20.0 |
| Obtain Building Consent | 20.0 |
| Owner accepts cost & signs stage 2 civil contract | 5.0 |
| call tenders for road | 20.0 |
| excavate and form entire road | 40.0 |
| order transformer | 10.0 |
| assemble contract for Villa 3B | 20.0 |
| prepare master landscape plan | 30.0 |
| owner approves landscape plan | 10.0 |
| obtain necessary approvals | 20.0 |
| prepare landscape stage 2 plan | 30.0 |
| Owner approves stage 2 landscape plan | 5.0 |
| prepare landscape documents | 10.0 |
| obtain landscape tender | 20.0 |
| Owner approves tender | 5.0 |
| implement landscaping | 20.0 |
| negotiate cost for 4 Villas | 15.0 |
| Owner accepts cost & signs Stage 2 construction contract | 5.0 |
| Stage 2 construction of 4 Villas | 195.0 |
| Construction 75% complete | 65.0 |
| STAGE 2 COMPLETED | 1.0 |
| Apply for Building Consent for Stage 2 Villas | 25.0 |
| Pay subdivision bond | 5.0 |
| excavate for Stage 2 building platforms | 30.0 |
| code of compliance approved | 20.0 |
| install FF&E | 5.0 |
| excavate trenches | 30.0 |
| lay water and sewer services | 40.0 |
| SERVICES COMPLETED | 1.0 |
| lay cable | 20.0 |
| lay telecom cables | 30.0 |
| defects and liabilities period | 1.0 |
![]()