Plan: Exhibit Gallery Development

Plan ID: 512 (Use this number to open the plan. Here's how.)

Email this plan summary to a friend or colleague...

Tag with: digg | del.icio.us | reddit |YahooMyWeb | Furl

Plan notes: This was originally developed in response to a request for proposals. I believe I can share it because we did not get the job and all proprietary info has been removed. The client did like our plan.

Version: 1. Last updated: Thu Jul 13 15:14:57 MDT 2006.

Plan Summary Report

Plan Top Level
NameDuration
start0
Kickoff Meeting - Project Initiation (Key Players)1
Research Concept Prepare Workship Resources10
Concept Workshop - Block out spaces for 1st gallery - Block out specific exhibits for 2nd gallery2
Create fundraising materials8
Overall Design for 1st Gallery8
Prepare for 2-day Intensive Design Workshop - Research - Resource Review - Exploration of ideasf10
Site Planning - 2nd gallery objectives articulated - circulation - sight lines - story line - General gallery Interpretation plan - Aesthetic plan10
2-day Intensive Design workshop - Concept Development Agreed - (List the points that must be signed off during the 2 days.) [Note the earliest day is fixed on a Friday. It might be useful to hold this on the Friday-Monday with some work done on the weekend]2
Add more sections or subprojects as required1
Plan physical changes to the building - cost - design - seek approval10
Exhibit Component Design #2 - describe unit objectives - prove concept - test interactive concept15
Exhibit Component Design #1 [Expect many components, each to have its own sub-project] - describe unit objectives - prove concept - test interactive concept 12
Schematic Design Complete - Identify physical elements - integration of elements - location withing physical space3
Complete site plan5
Complete Exhibit Designs - Costing10
Complete prototype testing where required10
Negotiate & Conclude Agreements with Suppliers & Fabricators - Provide all drawings and specifications for fabrication - submit to qualified fabricators - receive quotes & value engineering - award contracts15
Design Development Complete - developed schematic design - fully detail exhibits - proto-type testing done0
Fabrication Drawings [This is tight and CP. If required, put more resources to this so as to not stall project. Some of this may be done earlier.]7
Update Production Schedule - Site preparation - Props - Exhibits - Graphicx - Documentation - Contract assistance - Docent training - Avoid conflicting engagements5
Fabrication Drawings complete - Fabrication documents - props/exhibits/graphics schedule0
Supervise Exhibit Development - display construction & delivery - installation & testing - site preparation - site finishing [This 4-week process will probably evolve into several sub-projects. Some may be underway earlier.]20
Implementation - Construction/production/fabrication - building modification - exhibit fabrication - show production - installation & testing of exhibits0
Openings - Donor Previews - media events - Gala event8
Exhibit is complete and open0
Concept design - 2nd exhibit components - overall 2nd gallery10