Plan: BIAL Nuance Schedule
Plan ID: 1220 (Use this number to open the plan. Here's how.)
Whether or not you're a veteran project manager, SharedPlan provides you with powerful yet easy to use tools that support the success of your projects.Plan notes: PORT BIAL
| Name | Duration |
|---|---|
| 02) Presentation of Final Scheme Designs: Duty Free & Cocoon (Zurich). | 2.0 |
| 19) Detailed Briefing of Grottini Shopfitter & Handover of Final Drawing Package. | 2.0 |
| 07) All Stores: Design Schemes Frozen. | 1.0 |
| 09) Final Technical Drawing Package Production commences. (Final Construction Issue). | 20.0 |
| 16) Final Checking of Drawing Package & Sign off Internally. (Portland). | 2.0 |
| 17) Final Approval of drawing package from Nuance. | 1.0 |
| 06) Presentation of Final Nuance Retail Design to BIAL. For feedback prior to freezing. (India) | 1.0 |
| 14) Nuance Retail Design Intergration with HVAC & Building Security (WINTERS). | 3.0 |
| 08) Lighting Scheme Design. (RCPs to Siteco, for scheme design). | 13.0 |
| 04) Presentation of Final Scheme Designs: Shoppers Stop / Sound & Vision / Crossword / Life Spirit / BD Choc / La Moda. (Zurich). | 2.0 |
| 01) Fixturing & Scheme Development: Duty Free & Cocoon. | 5.0 |
| 11) HVAC Scheme Proposal Design & Calculations. | 5.0 |
| 12) HVAC: Briefing of Winter Engineering of Nuance Retail Scheme. | 1.0 |
| 15) Coordination of Nuance Retail Design with HMS Host F&B Consultants (Dreeson). | 1.0 |
| 13) Security Systems Scheme Proposal Design. | 9.0 |
| 03) Fixturing & Scheme Development: Shoppers Stop / Sound & Vision / Crossword / Life Spirit / BD Choc / La Moda. | 10.0 |
| 05) Update of changes to Nuance Retail Scheme | 7.0 |
| 10) Production Of Material Specification Doc. | 20.0 |
| 18) Final Construction Drawing package Issued to Nuance / BIAL / Grottini. | 1.0 |
| 20) Detailed Breakdown Costing of Project By Grottini. | 7.0 |
| 21) Submittal of Project costs from Grottini to Nuance. | 1.0 |
| 22) Approval of Project Construction costs and Appointment of Grottini. | 5.0 |
| 23) Grottini: Production of Final Construction Drawings for Nuance Areas. (Note this will be phased by shop) | 20.0 |
| 24) Grottini: Production of Prototypes for final approval by Nuance. | 9.0 |
| 25) Grottini / Nuance: Approval of prototypes for production. | 1.0 |
| 30) Grottini onsite Installation of All Stores in PTB. BIAL | 30.0 |
| 28) Crating & Shipping of all shop Interiors to India. (Mumbai) | 22.0 |
| 29) Customs Clearence & Shipping of containers to Bangalore | 10.0 |
| 27) Nuance Inspection & Sign off of Final Freetanding Fixtures. | 5.0 |
| 31) Nuance Inspection & Snagging of All Stores. | 5.0 |
| 32) Grottini Completion of all snagging. | 8.0 |
| 26) Grottini: Full Production of all Stores | 35.0 |
| 33) Grottini HandoverAll completed stores to Nuance, For merchandising. | 1.0 |
![]()